Kathmandu-Terai/Madesh Expressway Project Needs Rs. 135 Billion Budget

Kathmandu-Terai/Madesh Expressway Project Needs Rs. 135 Billion Budget

Feb. 11, 2022, 9:01 a.m.

The Kathmandu-Terai/Madhes Fast Track (Expressway) Project office Thursday said that a budget of Rs. 135.68 billion is required in the next three fiscal years to complete the project in time reports The Rising Nepal.

The project, which has spent Rs. 25 billion so far, has prepared a plan and program to spend over Rs. 135 billion in the next three years.

Brigadier General and spokesperson for the Nepali Army Headquarters Narayan Silwal said that a budget of Rs. 55.50 billion is needed in the coming fiscal year in 2079/80 alone.

spokespeson.jpg

For the Expressway being constructed by the Nepali Army, a budget of Rs. 45.66 billion is required for the fiscal year 2080/81 and Rs. 34.52 billion for the fiscal year 2081/82, said Silwal.

“We have already reached agreements on several packages for constructing the tunnel and sky bridges along with the project site, the major infrastructures to be built to complete the project,” Brigadier Silwal said.

A spokesperson for the Finance Ministry Ritesh Kumar Shakya said that the Ministry has ensured managing the required budget for the completion of the project in time. “In this regard, our another Joint Secretary Baburam Subedi of the ministry on Wednesday’s meeting with lawmakers has also given word to arrange needed budget for the project,” Shakya said.

But for that, he urged the project officials to come up with a reality-based budgetary plan. He said the Ministry of Finance was facing problems in arranging the necessary budget for the project due to a lack of a realistic plan.

Similarly, the NA has already approved the design of the tunnel and the bridges to be built after contracting it with two different Chinese companies.

The contract for the construction of the tunnels had been signed in two packages.

Spokesperson Silwal informed that the design made by the contractors as per the contract under EPC model was approved by the army and sent to the construction site. "They have started surveying the tunnel site," he said.

The cost of these two packages is Rs. 44 billion. Under one package, the construction of two tunnels and bridges will be started at Dhedre of Makwanpur (1.37 km from Simpani to Chalise Kholsi) and at Lendanda (1.4 km from Ghattepakha to Bandrekholsi) reports The Rising Nepal.

More on National

The Latest

Latest Magazine

VOL. 18, No. 09, December.13, 2024 (Mangsir-28. 2081) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 18, No. 08, November.29,2024 (Mangsir-14. 2081) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 18, No. 07, November.15,2024 (Kartik-30. 2081) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 18, No. 06, October.25,2024 (Kartik-09. 2081) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75