The per unit energy generation cost of the Upper Karnali storage project operating at a very high water head of around 400 meters, as mentioned earlier, would be very low. The per unit energy generation cost of this project in comparison with such e
By Dr. A.B. Thapa Oct 18, 2014
The firm installed capacity of the Upper Karnali storage project could be raised even further up to 8000 MW if the peaking hour is limited to daily 3 hours as in case of the proposed 900 MW variant.
By Dr. A.B. Thapa Aug 17, 2014
The Gandak River Treaty signed between Nepal and India in 1959 had totally curtailed our country’s right to use freely the water of rivers in Gandak basin within our territory except in three months of the monsoon season when all Gandak trib
By Dr. A.B. Thapa Sep 13, 2013
Peoples of Nepal and India must be alarmed that that our region is quickly heading for far worse Kosi flood disasters. Certainly, the scale of the 2008 Kosi flood disaster would be just the tip of the iceberg by comparison with th
By Dr. A.B. Thapa Jan 14, 2013